READING THE RESPONSE: VOLTAGE

What “Voltage Fluctuation Over 2%” Means

At first glance it may look as though “it can be connected”, but additional equipment, operating conditions or renewed consultation can change the project’s viability. Before you buy, we read the response down to its small conditions.

* This page provides general information to support your decisions. Connection conditions differ depending on the response and individual consultation with the general transmission and distribution operator.

CONCLUSION

Over 2% is not an “immediate no”;
it is a sign to check additional countermeasures.

If the response indicates that the voltage fluctuation at the connection point may exceed 2%, check whether countermeasures are needed, who carries them out, the cost, the schedule and the operating conditions. It is important not to jump to conclusions about whether connection is possible or about the additional cost from the entry alone.

BUY BEFORE CHECK

Do not judge it a “cheap project”
on the grid connection construction cost alone.

  • Whether the countermeasure equipment is paid for by the developer
  • Whether there are limits on output or on charging and discharging
  • Whether the time for design, testing and consultation increases

VOLTAGE RANGE

“Over 2%” is the entry point for reading the conditions in the response

Charging and discharging the batteries, and connecting equipment to and disconnecting it from the grid, raise and lower the voltage at the connection point. If the response indicates that the range of fluctuation may exceed 2%, you may need to look at control on the equipment side, additional devices, operating conditions and so on.

Important: The diagram is a simplified illustration of how the judgment works. The wording and conditions in the response differ from project to project. Do not draw a conclusion from the words “Over 2%” alone; check the operation it applies to and the countermeasures required.

THREE IMPACTS

If overlooked, it affects 3 things: cost, schedule and operation.

01

Additional CAPEX

Reactive power control, changes to the transformer specifications and studying options such as an SVC or STATCOM may increase the costs of equipment, design, construction and testing.

02

Schedule and site conditions

Equipment selection, recalculation, checks with manufacturers, consultation with the general T&D operator and securing space for additional equipment may affect the schedule.

03

Operating limits

If conditions are attached on charge and discharge output, power factor, connection and disconnection, control mode and so on, you need to recheck the planned operation and the revenue assumptions.

ANSWER SHEET CHECK

7 items to check in the response

  • 1
    Under which operating conditions it exceeds 2%

    Check the scenario it applies to, such as charging or discharging, connection or disconnection, or maximum output.

  • 2
    Who carries out the countermeasures

    Check the division of responsibility: the general T&D operator’s side or the developer’s equipment.

  • 3
    Scope of the grid connection construction cost

    Check whether the costs of additional countermeasure equipment, design and testing are included.

  • 4
    Control functions required

    Check that requirements such as power factor, reactive power and constant-voltage control match the PCS specifications.

  • 5
    Installation space for additional equipment

    Check the panels, transformers, compensation devices, maintenance access routes and clearances.

  • 6
    Additional steps for consultation and testing

    Check whether analysis submissions, manufacturer studies, on-site tests and the like are needed.

  • 7
    Reflecting it in the finances

    Re-estimate project viability on the basis of additional CAPEX, the schedule and operating limits.

The hands of a staff member checking the reply to the connection study and a grid diagram

COUNTERMEASURE OPTIONS

We do not decide on additional countermeasures by picking one device up front.

We compare options by combining the grid conditions, PCS capability, transformer specifications and the operating plan. The table below shows general examples of what is studied and does not show the requirements for any individual project.

Example studied Points to check Main impact on project viability
PCS reactive power and voltage control Supported modes, available output range, warranty conditions, compatibility with operation in other markets Constraints on active power, effort for setup and verification
Adjusting the transformer and tap specifications Rating, impedance, tap range, conditions at the receiving point Equipment specifications, delivery time, design changes
Compensation equipment such as SVC or STATCOM Capacity needed, response performance, installation area, maintenance, connection consultation Equipment cost, cost of works, space, schedule
Adjusting the operating conditions Limits on charge and discharge output, power factor, connection and disconnection, time of day and so on Re-evaluation of market operation and revenue assumptions
Grid-side countermeasures or a change of connection method Whether reinforcement, a dedicated line, a change of connection point and the like can be discussed Grid connection construction cost, time required, whether the project can go ahead

BEFORE PURCHASE

Before you buy, re-estimate, including additional countermeasure costs.

If you share the response, the single-line diagram and the equipment specifications, we will sort out the issues that are easy to overlook and where to check next.

See what the free DD assessment covers
A surveyor checking a candidate battery storage site with drawings and a tablet
A candidate battery storage site where the grid equipment and surrounding conditions are being checked

FREE DESK DUE DILIGENCE

What the free DD assessment sorts out

Conditions in the response

We pick out key entries such as voltage fluctuation, special measures, the construction period and the grid connection construction cost.

Where to check further

Matters to check with the transmission and distribution operator, PCS and transformer manufacturers, and design firms.

Impact on project viability

Issues for reflecting additional CAPEX, the schedule and operating conditions in the finances.

Next decision

Options such as continuing with the purchase, negotiating terms, getting additional quotations or renewed consultation.

* This is a preliminary review based on desk research, public information and the documents you provide. It is not a design guarantee or a commitment on whether connection is possible, and it does not replace the formal judgment of the general T&D operator.

DOCUMENTS & FLOW

Even if your documents are incomplete, we can sort things out from where you are now.

A consultation meeting to check documents for a grid-scale battery storage (BESS) site

Documents that make the check easier

  • Reply to the connection study / reply to the connection application
  • Copy of the connection study application form
  • Single-line diagram / equipment configuration diagram
  • PCS and transformer specifications
  • Site location map, cadastral map, layout plan
STEP 1

Share documents

Only the documents you have at hand are fine.

STEP 2

Desk check

We cross-check the response conditions against the equipment and site conditions.

STEP 3

Sort out issues

We make the additional cost, the schedule and where to check visible.

STEP 4

Next decision

We sort out the options of buying, selling or renewed consultation.

FAQ

Frequently asked questions

If the response says “Voltage Fluctuation Over 2%”, does that mean the site cannot be connected?

It does not necessarily mean that connection is ruled out straight away. However, equipment countermeasures to limit the voltage fluctuation, control conditions or additional consultation may be needed. Check the relevant part of the response and its assumptions individually.

Is the cost of voltage fluctuation countermeasures included in the grid connection construction cost?

Not necessarily. Countermeasures required as equipment on the developer’s side may incur costs for design, equipment, construction and testing separately from the grid connection construction cost. It is important to separate out what each quotation covers.

Is an SVC or STATCOM always needed?

Not necessarily. We consider several options, including reactive power control by the PCS, the transformer specifications and the operating conditions, according to the grid conditions and the requirements in the response. Whether equipment is needed is decided through individual consultation and design studies.

Can the additional cost be fixed from the response alone?

It sometimes cannot be fixed from the response alone. We carry out a technical study together with the single-line diagram, the PCS and transformer specifications, the output conditions, information on the connection point and so on, and check with manufacturers, design firms and the general transmission and distribution operator as needed.

Can a seller of land also request a free DD assessment?

Whether you are a seller, buyer, developer or broker, we sort out the issues according to the documents you have. If documents are missing, we start by checking the information you should obtain next.

Can I consult you before I have a response?

Yes. However, the response or the results of an individual connection study are needed to formally confirm the conditions on voltage fluctuation. Based on the site conditions and the current status of your application, we will tell you which items to check first.