Creating success in grid-scale battery storage, together.

GRID CONNECTION

High-voltage grid-scale battery storage:
the connection study, grid connection process and costs

A high-voltage grid-scale battery storage system with an output under 2,000kW goes through the utility's connection study, applies for a contract based on the reply, and is connected to the grid only after connection approval is obtained. The reply to a connection study takes 3 months as a rule, and the study fee is paid separately to the utility. We take on each stage on request, from checking available grid capacity to acting for you in the contract application.

VOLTAGE

Size and configuration of a system connected at high voltage

What can be connected to a high-voltage distribution line is, as a rule, equipment with an output under 2,000kW per installer. The system assumed by REVIX's Nippachi Simulator (output 1,990kW, 4 NEXTES CE007 containerized battery systems, 8,332kWh in total) also falls within this range.

At this scale, a battery and a power conditioner alone cannot be connected to the grid. A transformer to match the voltage, substation equipment and the protection devices that disconnect the system from the grid in the event of a fault are designed as one system, and its single-line diagram, layout plan and elevation drawing are attached to the connection study application. The high-voltage drawing set (No.05, 49,500 yen incl. tax) is the menu item that produces these 3 documents.

FLOW

High voltageSteps up to the connection application

We proceed in stages, from checking whether your land can be connected to the grid to the application to the utility. Each stage can be ordered on its own, so you can also start by checking the available capacity first.

1

Available capacity check

We check whether the grid near the land has capacity available for connection.

No.03|¥11,000 incl. tax

2

Land assessment and site check

We check land conditions such as hazards and city planning, and the situation on site.

No.01 / 02 / 04

3

Drawings

We prepare the layout plan, elevation and single-line diagram needed for the connection study.

No.05|¥49,500 incl. tax

4

Connection study application

We apply to the utility for a connection study. The study fee is paid to the utility.

No.06〜08

5

Reply from the utility

Based on the reply, covering whether connection is possible, the grid connection construction cost, timing and so on, you move to the next decision.

6

Formal application (contract application)

If you go ahead with the project based on the utility's reply, we act for you in the contract application needed for grid connection, working with the parties involved.

No.09|¥110,000 incl. tax

* The lead time, the content of the reply and the grid connection construction cost vary with the utility and the grid conditions in the area. We will give you an individual outlook at the consultation.

* If you change a battery, PCS or other equipment that has already been applied for to equipment we handle, the equipment change application service (No.10) supports the change procedure. If the change calls for a new connection study, we handle it with the high-voltage re-study application (No.11).

PROCEDURE

High voltageProcedures with the utility, from preliminary consultation to grid connection

The "steps up to the connection application" above are the order of the work you ask REVIX to do. Here we follow the procedures with the utility in order and describe what is decided at each stage.

  1. Preliminary consultation (optional)A simple procedure to check, for example, whether there are connection restrictions on the nearby grid. There is no fee, and the reply comes within 1 month as a rule. It is not a promise that connection will be possible.
  2. Connection study (required)A study you must go through before the contract application. The reply covers whether connection is possible, the construction needed and an estimate of the grid connection construction cost (payable by the applicant), the construction period and operating constraints. For grid-scale battery storage, the charging side (the side receiving power from the utility) is studied as well. The reply can no longer be used once 1 year has passed from the reply date, and the study has to be done again.
  3. Contract applicationYou apply based on the reply to the connection study and pay a deposit. The deposit is later applied to the grid connection construction cost. For grid-scale battery storage, the application is accepted only when the generation-side (discharging) and demand-side (charging) applications are submitted together. The reply comes within 6 months as a rule, or within a period agreed with the utility. We handle this with the formal application service (No.09, 110,000 yen incl. tax).
  4. Connection approval and the construction cost agreementWithin 1 month of the approval reply, you sign the agreement for the grid connection construction cost. If you miss the deadline or do not pay the cost, the capacity secured is cancelled. For contract applications accepted on or after October 1, 2026, you also have to submit documents showing your right to use the land (such as a property register or a lease agreement) within 2 months of approval as a rule. For details, see the BESS NEWS article "Land documents for grid-scale battery storage: due within 2 months of approval for applications accepted from October 1".
  5. Construction and grid connectionThe utility's work and the installer's equipment work go ahead, and operation starts once the necessary tests and checks are complete.

STUDY

High voltageConnection study fee and time to reply

When you apply for a connection study, you pay the utility a study fee for 1 site and 1 study at a time. The current fee is 220,000 yen incl. tax, and the utility study fee in the price list (No.08) is this amount. Because it is paid to the utility, it is not included in the high-voltage connection application set (108,900 yen incl. tax).

The reply comes within 3 months of acceptance of the application as a rule (2 months as a rule for systems under 500kW that use an inverter). But "acceptance" counts from the day the documents are found complete and payment of the study fee is confirmed, and the Organization for Cross-regional Coordination of Transmission Operators (OCCTO) advises that checking and correcting the documents before that point takes about 2 months in practice. We recommend allowing around half a year in your schedule from preparing the application to the reply.

From April 2026, high-voltage connection studies for the distribution grid use a new practice: at the time of application you state "how much grid connection construction cost you can bear" and "whether you accept reinforcement of the upstream grid". If it becomes clear during the study that the conditions you stated cannot be met, you receive an early reply that connection is not possible. In that case the study fee is not refunded. The upper limit needs to be decided in advance, working back from the profit and loss of your business plan. For details, see the BESS NEWS article "What changes in connection studies from April 2026? New high-voltage forms and early replies".

Note that a national advisory council has started discussing a uniform nationwide increase in the connection study fee for grid-scale battery storage (as of October 2026, the amount and timing are undecided). For details, see the BESS NEWS article "Proposal to raise the 220,000 yen connection study fee, starting with grid-scale battery storage, nationwide".

LIMIT

High voltageThere is a cap on the number of connection study applications

From August 1, 2026, for high-voltage and extra-high-voltage grid-scale battery storage, there is a cap on the number of connection studies one business can have under way at the same time with the same utility. At TEPCO Power Grid it is 11. Applications over the cap are not accepted and are not put on a waiting list, so you apply again once a slot opens.

If you want to study several candidate sites at the same time, the order in which you submit the sites for connection studies directly shapes how the project moves forward. Narrowing down the candidates with the available capacity check (No.03) and the land survey (No.04) before applying keeps you from using up the limited slots.

CAPACITY

High voltageAvailable capacity is a guide before you apply

General T&D operators publish the available capacity of each transmission line and substation. With the available capacity check (No.03, 11,000 yen incl. tax), we check the capacity available at that time on the grid near the candidate site.

Available capacity changes day by day with applications from other businesses. Even on a grid with capacity available, reinforcement work may be required, or conditions may be attached to charging and discharging. The final conditions are confirmed in the reply to the connection study.

APPLICATION COST

High voltageApplication fees (price list)

This is the list of high-voltage application menu items. The connection application set (No.07) includes the available capacity check, the land survey report, the drawing set and the connection study application (No.03 to 06). The formal application (contract application) that follows the reply to the connection study, and changes to equipment already applied for, can be ordered as the application services No.09 and 10. A re-study required by an equipment change or similar is handled under No.11.

* The table scrolls sideways

No.CategoryItemExcl. taxIncl. taxNotes
01Site checkOnline site check (remote)¥20,000¥22,000You take the photos and measurements on site. We guide you online on where to shoot and measure, and check that no data is missing. We do not compile the data into materials or prepare a survey report.
02Site checkSite check (site visit)¥110,000¥121,000Travel and accommodation costs, where incurred, are charged at cost.
03Land assessment, single itemAvailable capacity check¥10,000¥11,000Check of the available capacity at the current stage.
04Land assessment, single itemLand survey report¥30,000¥33,000Survey report on hazards, city planning, noise and buried cultural property.
05High voltage, single itemHigh-voltage drawing set¥45,000¥49,500Layout plan, elevation, single-line diagram.
06High voltage, single itemHigh-voltage connection study application¥50,000¥55,000When drawings are supplied. We prepare and submit the connection study application documents for you. If you withdraw the application after receiving the reply on the estimated construction period, the connection study fee is refunded.
07High voltage, setHigh-voltage connection application setSET¥99,000¥108,900Set contents: No.03, No.04, No.05 and No.06 are included. Application form, single-line diagram, layout plan, submission and corrections after acceptance. The utility study fee of 220,000 yen (incl. tax) is charged separately. Electrical work is not included. For the refund conditions on the connection study fee, see No.06. The formal application (contract application) is not included (No.09).
08Connection study feeUtility study fee¥200,000¥220,000Paid to the utility.
09Application serviceFormal application service¥100,000¥110,000Acting for you in the contract application (formal application) to the utility. We will tell you the scope of work according to the status of your application. The fee is charged regardless of the outcome of the application. The deposit and the grid connection construction cost are required separately.
10Application serviceEquipment change application service¥100,000¥110,000Applies to changes to equipment we handle. Depending on the change, it may be necessary to check whether a connection study is required, or to carry out a re-study. Equipment purchase and replacement work costs are not included.
11High voltage, single itemHigh-voltage re-study application¥50,000¥55,000Includes replacing documents when the prescribed forms change, and handling the correspondence on the application.
  • Consumption tax of 10% is added to the prices shown excluding tax (shown alongside in the incl. tax column).
  • Even when you use the high-voltage connection application set, the utility study fee of 220,000 yen (incl. tax) is required separately (paid to the utility).
  • For the site check (site visit), travel and accommodation costs, where incurred, are charged at cost.
  • Electrical work is not included in the set.
  • The formal application service and the equipment change application service are charged regardless of the outcome of the application. The same applies when a re-study becomes necessary, or when the utility's reply means that no contract or grid connection follows. The deposit, the grid connection construction cost and other payments to the utility may be required separately.
  • The equipment change application service applies to changes to equipment we handle. The cost of batteries, PCS and other equipment, and replacement and installation work, are not included.

CHANGE

High voltageChanging the equipment can mean redoing the study

A connection study is carried out under the conditions at the time of application: the battery, PCS, output, charging power and so on. If the content of the application form changes, another connection study may be needed. We handle changes to equipment we handle with the equipment change application service (No.10, 110,000 yen incl. tax), and re-studies with the high-voltage re-study application (No.11, 55,000 yen incl. tax).

DATA

High voltageHigh-voltage grid access in numbers

According to figures compiled by the Organization for Cross-regional Coordination of Transmission Operators, 28,927 connection studies were accepted in fiscal 2025, about 2 times the previous fiscal year. By type of power source, batteries account for 86%. On the other hand, as of the end of June 2026, the grid-scale battery storage actually connected to the grid was 1.28 million kW, a wide gap from the about 211 million kW of accepted connection studies. For details, see the BESS NEWS article "Batteries overtake solar in connection studies, reaching 66%".

For contract applications, of the 3,563 answered in fiscal 2025, 346 (9.7%) took longer than the standard 6 months. The main reason was incomplete application forms. REVIX prepares the application form and handles corrections after acceptance so that no time is lost at this stage.

SECURITY

High voltageCommunications equipment requirements from April 2027

High-voltage batteries whose contract application is made on or after April 1, 2027 are expected to be required to use products certified at "JC-STAR★1" or higher for equipment with internet communication functions (such as power conditioners and EMS) (a proposal under public comment since October 2026). Because the judgement is made by the acceptance date of the contract application, the timing of the application and the choice of equipment are considered together. For details, see the BESS NEWS article "High voltage from April 2027, low voltage under 50kW from October 2027: JC-STAR becomes a requirement".

POINTS

High voltageWhat to know before you apply

The reply may come with conditions

In addition to whether connection is possible, the reply includes the grid connection construction cost, the timing of the work and operating conditions. We also guide you on how to read the reply and on the next decision.

We check the land conditions in parallel

Even if the grid has capacity available, land conditions such as hazards and city planning may stop the plan from going ahead. Because there is also a deadline for submitting land documents after the contract application, we recommend combining this with the land survey report (No.04, 33,000 yen incl. tax).

Discuss connection conditions or place an order

If you know where the land is, we can tell you which menu item to start from.