01Electrical safety management for low-voltage battery storage stations
“It is low voltage, so no procedures are needed” is wrong.
Even at 49.9kW, a chief electrical engineer and safety regulations are required.
Is this in your simulation?
A stand-alone grid-scale battery storage station cannot be treated the same as a household battery just because it is “low voltage” and “49.9kW”.
Stand-alone low-voltage grid-scale battery storage station
Chief electrical engineer structureRequired
Notification of safety regulationsRequired
Battery co-located with solar
(solar of 10kW or more and under 50kW)
Chief electrical engineer structureExempt
Notification of safety regulationsExempt
Our approachBased on the candidate site, the equipment configuration and the quotation, we sort out the safety structure and costs required.
See details: the 3 obligations the installer prepares for
The 3 obligations the installer prepares for
- Set up a chief electrical engineer structureEven when outsourcing, check the eligibility requirements and the prescribed approval procedure.Electricity Business Act, Article 43
- Establish and notify safety regulationsDecide on and notify the rules for inspection, operation, responses to abnormalities and records.Electricity Business Act, Article 42
- Keep up inspections and responses to abnormalitiesMaintain conformity with technical standards. Record conditions and responses, and decide in advance who is in charge and the contact for abnormalities.Electricity Business Act, Article 39
Even at low voltage, procedures differ by type of equipment
Even equipment below the size covered by construction plan notification and similar requires a safety structure, safety regulations and maintenance of conformity with technical standards.
Both stand-alone battery storage stations and batteries co-located with solar need to maintain conformity with technical standards. Batteries with a capacity over 20kWh are subject to accident reporting (from November 20, 2025).
* Solar is not uniformly “exempt from safety requirements” either. Batteries attached to homes or to solar are treated differently from stand-alone battery storage stations. How the rules apply differs with the configuration and size of the equipment.
Sources: Electricity Business Act, Articles 39, 42 and 43 / Ordinance for Enforcement of the Electricity Business Act, Article 52, Paragraph 2 / Ordinance on Reporting Related to Electricity (in force from November 20, 2025) / Ministry of Economy, Trade and Industry, “Guide to Installing Power Storage Devices (Batteries) and Battery Storage Stations” / Kanto-Tohoku Industrial Safety and Inspection Department, “Approval System for Outsourcing” (checked on October 27, 2026)