HIGH-VOLTAGE BESS / INVESTOR
Understand the cost through its breakdown.
High-voltage grid-scale battery storage: how to read the cost and price breakdown
In a high-voltage investment decision, what matters is not the size of the total but seeing clearly "what costs how much, and what is not included". This page uses the same cost structure as the Nippachi Simulator, our high-voltage revenue simulator.
Key points on this page
- Total investment = design, equipment and construction cost + land rights cost (land price plus grid rights cost).
- Worked example: design, equipment and construction cost of about 520 million yen, plus grid rights and land, for a total example of about 640 million yen.
- If the land is leased, an annual rent is booked as an operating cost instead of the land rights cost.
BREAKDOWN
The costs that make up the total investment
The same cost structure as the estimate in the Nippachi Simulator
Design, equipment and construction cost
The cost of the complete system, excluding the land rights cost. It is added to the total investment and is subject to depreciable asset tax. Worked example: about 520 million yen.
Land rights cost (when the land is purchased)
The land price plus the grid rights cost. It is added to the total investment. Depreciable asset tax and fixed asset tax on the land are not included.
Land rent (when the land is leased)
If the land is leased, the annual rent is booked as an operating cost, free of consumption tax (it is not part of the total investment).
What moves the initial and operating costs
Costs such as connection, site preparation, maintenance and insurance vary with the conditions of each project. We check them individually, together with the specifications, warranty terms and maintenance plan.
TABLE
What is included, what is not
The figures and categories follow the Nippachi Simulator currently published
| Item | Included in the total investment | Not included (handled separately) |
|---|---|---|
| Equipment | Design, equipment and construction cost (complete system) | Variable items such as connection and site preparation, which depend on the project |
| Land (purchased) | Land price + grid rights cost | Fixed asset tax on the land and depreciable asset tax |
| Land (leased) | None | Annual rent (booked as an operating cost) |
* The worked example and cost structure follow the published estimate in the Nippachi Simulator. Actual costs are estimated project by project, after checking the equipment cost, connection cost, operating conditions, financing, tax and more.
Go to the Nippachi Simulator (estimate form with actual figures).
FAQ
Frequently asked questions
About the assumptions and how to check them
Is the worked example shown here an actual quotation?
How can I check the effect of costs coming in higher than planned?
Once you understand the breakdown, run an estimate on your own conditions
Enter your land conditions and land rights cost to see the payback outlook.
Run an estimate in the Nippachi Simulator →