It is fine to start with the documents you have.

Required Documents Guide for High-Voltage Projects (for Investors)

In a high-voltage project study, documents are not only "for submission." They are also design information for aligning the business conditions. We have listed, in order, the documents needed at each stage of the study.

Key points on this page

  • You can consult us on an initial check of site suitability with the documents you have, such as the location, lot number and on-site photos.
  • As the study progresses, the registry and cadastral map, the reply to the connection study, and design and safety-related documents are prepared step by step.
  • Requirements and documents to submit vary by equipment category, location, connection destination, application type and administrative decisions, so we advise case by case.

CHECKLIST

Required documents checklist by stage

Listed in the order they are needed. You can start a consultation with the first STEP alone

STEP 1

Initial consultation and site suitability check

You can start consulting from this stage
  • Location, lot number and mapThis is all you need Used to identify the site
  • On-site and surrounding photos Materials showing road access and delivery conditions and the expected equipment scale make it easier to sort things out
STEP 2

Survey and study

Once the study of the candidate site moves forward
  • Registry information, cadastral map, survey drawings, etc. Used to check the current state, road access and the status of land rights
  • Land-related confirmation documents and supporting materials Used to study the layout and delivery
STEP 3

Grid and contract procedures

When moving on to the procedures
  • Reply to the connection study and contract application documents Used for grid access procedures
  • Land contract and documents showing rights to the land Used to sort out contracts and land rights
STEP 4

Design, construction and safety

When preparing for the start of construction
  • Detailed design drawings and protection coordination materials Used to check the equipment design
  • Construction plan and materials for consultations with the authorities Used for construction and administrative procedures
  • Safety regulations and chief electrical engineer documents Used to set up the safety management structure

* The above are general check items and typical examples. Requirements and documents to submit vary by equipment category, location, connection destination, application type and administrative decisions. For the formal documents to submit, the latest guidance from the application destination takes priority, and we advise case by case.
For the conditions themselves, such as site area and road access, see the site requirements (land, grid and layout).

Even if your documents are not complete, you can consult us with what you have

The required documents change with each stage of the study. We decide the order in which to gather documents, reflect the decisions made at each stage in the next design step, and update the documents to the accuracy needed at that stage.

FAQ

Frequently asked questions

On preparing documents

Can I consult you even if my documents are not complete?
It is easier to sort things out if you have materials showing the location of the candidate site, registry information or the cadastral map, on-site photos, road access and delivery conditions, and the expected equipment scale. Even if these are not all in place, you can consult us with what is known.
Can I move forward even if the land rights have not been sorted out?
You can consult us on an initial check of site suitability. However, at the stage of moving on to grid access procedures, contracts and the start of construction, land-related confirmation documents and the rights to the land may need to be sorted out.

Start by consulting us with the documents you have

A consultation shows you which documents to gather next and the order of checks.

Consult us with just the site location first →

Published: August 9, 2026 / Last updated: August 9, 2026 | Basis for the content: based on the information on the Site Requirements and Documents page